Hi,

I have one issue regarding ME21N transaction. When I try to create PO and give PO qty then PO qty automatically changes according to min/max lot sizes or according to rounding value given in material master in MRP1 view.

But I do not want the PO qty to be changed. Also I cannot remove the values from material master as those are required for another purpose.

So I think there should be some user exit which can stop automatic PO qty change.

Can anybody help me on this?

Thanks and regards,

Harish

1 REPLY 1

Former Member
0 Kudos

Hi,

Please check enhancement MM06E005 (SMOD).

Also have a look at the following exits: EXIT_SAPMM06E_012 EXIT_SAPMM06E_014.

You can also consider the BADI ME_PURCHDOC_POSTED & ME_CIN_MM06EFKO

BADI ME_PROCESS_PO_CUST.

regards,