In MD02 - No procurement proposals changed

vallamuthu_madheswaran2
Active Contributor
0 Kudos
327

Hi Friends,

I have executed MD02. In database statistics, "No procurement proposals changed". How to correct it.

Thanks with regards,

Vallamuthu M.

2 REPLIES 2

raymond_giuseppi
Active Contributor
0 Kudos
282

Did you already there check if there are already procurement proposals like PRs and POs and those proposals are enough for your PIR.

Else provide more information (e.g. Planning strategy used) and better tags (PP, MRP, 🔮?)

vallamuthu_madheswaran2
Active Contributor
0 Kudos
282

Hi Raymond,

Thanks for your answer.

we are not able to create dependent requirements in MD02, if we are using Special procurement which was created by a functional consultant.

However dependent requirements are created for standard procurement.

Thanks with regards,

vallamuthu M