2006 Sep 02 8:08 AM
while creating the Purchase Req. if my Budget exceeds then the system give the error that the Budget excees by so much qty.
my requirement is that can i get the amount of budget consumed for the PR, for different Cost Center or Fund Center wise.
i hope this cleare my query
abhishek
2006 Sep 02 7:09 PM
Are you on 4.7 or 4.6C or some other version? If 4.7, are you using BCS or FBS?
At what point do you want to know the budget consumption - at PR time or some later time for reporting?
Rob
2006 Sep 04 4:20 AM
dear Rob,
i am using 4.7
i want it later stage for Reporting purpose
abhishek
Message was edited by: Abhishek Suppal
2006 Sep 04 4:47 AM
BCS or FBS? (I'm not really sure if this matters or not but it might help).
Rob
2006 Sep 04 7:06 AM