Application Development Discussions
Join the discussions or start your own on all things application development, including tools and APIs, programming models, and keeping your skills sharp.
cancel
Showing results for 
Search instead for 
Did you mean: 

BADI documentation

Former Member
0 Kudos
2,271

hai,

T-code : MM01

BADI : BADI_MATERIAL_CHECK

documentation is not being displayed.

how to solve this problem.

1 ACCEPTED SOLUTION

Former Member
0 Kudos
411

Hi Ravi,

Which Environment your working,i checked in ECC6.0,Its Displaying Documentation,i am givng the documnetation bellow,

1.Run tcode SE18 Select RadioButton BADINAME

Here u have to give BADI_MATERIAL_CHECK .

click on Display

and then one tab is there in toolbar Click on Documentation

then itdislays the following,

HY SIMGBADI_MATERIAL_CHECK

Use

You can use the Business Add-In BADI_MATERIAL_CHECK to implement your own field checks and partial changes to material master data.

The CHECK_DATA method is available to you to do so.

Activities

After calling up the IMG activity, a dialog box appears, in which you can enter a name for the implementation.

If you have already made other implementations for this BAdI, another dialog box appears, in which the existing implementations are displayed. In this case, choose Create, and proceed as follows:

1. In the dialog box, enter a name for the BAdI implementation in the Implementation field, and choose Create.

The screen for creating BAdI implementations is now displayed.

2. Enter a short text for the implementation in the Short text for implementation field.

3. From the tab index, choose Interface.

The Name of implemented class field is already filled on the tab page, as a class name was automatically assigned to the implementation when you named it.

4. Save your entries, and assign the implementation to a development class.

5. Place the cursor on the method, and double-click to enter method processing.

6. Enter the code for the implementation between the statements method <Interface name> ~ <Name of method> and endmethod.

7. Save and implement your code. Return to the Edit Implementation screen.

8. Save the entries on the Edit Implementation screen.

Note: You can also create an implementation, and then activate it at a later time. In such a case, end the processing stage at this point.

9. Choose Activate

The code you stored in the method will be run when the application program is executed.

Cheers,

Phani,

Points if helpful.

4 REPLIES 4

Former Member
0 Kudos
411

Search the net !

Former Member
0 Kudos
412

Hi Ravi,

Which Environment your working,i checked in ECC6.0,Its Displaying Documentation,i am givng the documnetation bellow,

1.Run tcode SE18 Select RadioButton BADINAME

Here u have to give BADI_MATERIAL_CHECK .

click on Display

and then one tab is there in toolbar Click on Documentation

then itdislays the following,

HY SIMGBADI_MATERIAL_CHECK

Use

You can use the Business Add-In BADI_MATERIAL_CHECK to implement your own field checks and partial changes to material master data.

The CHECK_DATA method is available to you to do so.

Activities

After calling up the IMG activity, a dialog box appears, in which you can enter a name for the implementation.

If you have already made other implementations for this BAdI, another dialog box appears, in which the existing implementations are displayed. In this case, choose Create, and proceed as follows:

1. In the dialog box, enter a name for the BAdI implementation in the Implementation field, and choose Create.

The screen for creating BAdI implementations is now displayed.

2. Enter a short text for the implementation in the Short text for implementation field.

3. From the tab index, choose Interface.

The Name of implemented class field is already filled on the tab page, as a class name was automatically assigned to the implementation when you named it.

4. Save your entries, and assign the implementation to a development class.

5. Place the cursor on the method, and double-click to enter method processing.

6. Enter the code for the implementation between the statements method <Interface name> ~ <Name of method> and endmethod.

7. Save and implement your code. Return to the Edit Implementation screen.

8. Save the entries on the Edit Implementation screen.

Note: You can also create an implementation, and then activate it at a later time. In such a case, end the processing stage at this point.

9. Choose Activate

The code you stored in the method will be run when the application program is executed.

Cheers,

Phani,

Points if helpful.

Former Member
0 Kudos
411

Hi Ravi,

Go to SE18 - Tcode for Definition of BAdi.

There you click the BAdi name radio button, and give your badi name BADI_MATERIAL_CHECK .

Click on Display button, there in Application tool bar there you will find Documentation button, when you click on that you will find documentation. By that you can search and go with your requirement.

Reward points if useful.

Cheers,

Swamy Kunche

Former Member
0 Kudos
411

-