Application Development Discussions
Join the discussions or start your own on all things application development, including tools and APIs, programming models, and keeping your skills sharp.
cancel
Showing results for 
Search instead for 
Did you mean: 

AFAB - PRPS Relation (Network Relations - Work Breakdown Structure)

Former Member
0 Kudos
132

Hi Experts.

How can i find the relation between these two tables : AFAB-PRPS, i need to know wich Work Breajdown Structure are direct retaled with the Network relations in PS. Andy Ideas?, tnxs for your hlp.

1 ACCEPTED SOLUTION

former_member191977
Contributor
0 Kudos
63

AD03OBJTV - Plan data handling WBS objects, type and version

This is the table through which objnr is linked from AFAB.

AFAB & PRPS objnr is the field through which they are linked.

does this help you ? or else we can discuss more.

award points if it helps.

2 REPLIES 2

former_member191977
Contributor
0 Kudos
64

AD03OBJTV - Plan data handling WBS objects, type and version

This is the table through which objnr is linked from AFAB.

AFAB & PRPS objnr is the field through which they are linked.

does this help you ? or else we can discuss more.

award points if it helps.

0 Kudos
63

Vinni :

I've found the field you suggested, but when i check the values of both fields in both tables, they're different. Any Suggestions?.