    <title>Question Re: 'Anchor' time period in IBP in Supply Chain Management Q&amp;A</title>
    <link>https://community.sap.com/t5/supply-chain-management-q-a/anchor-time-period-in-ibp/qaa-p/12098711#M171894</link>
    <description>&lt;P&gt;Hi Dan,&lt;/P&gt;&lt;P&gt;Here is what you can do. Create another Key Figure : helper and load that with a value 1, in the buckets you need the value output in another key figure. in your case, first month of every quarter. This could be a CPI-DS job  scheduled monthly or you can do that using a manually maintained file using data integration and keep updating the buckets each month and updating the key figure.&lt;/P&gt;&lt;P&gt;Once you've loaded the helper key figure with 1 for required buckets,  create another calculated key figure and put a calculation to check if the helper key figure is 1 then this calculated key figure gets value from source key figure, else default it to null.&lt;/P&gt;&lt;P&gt;Thanks,&lt;/P&gt;&lt;P&gt;Nikunj&lt;/P&gt;</description>
    <pubDate>Thu, 12 Sep 2019 18:59:09 GMT</pubDate>
    <dc:creator>Former Member</dc:creator>
    <dc:date>2019-09-12T18:59:09Z</dc:date>
    <item>
      <title>'Anchor' time period in IBP</title>
      <link>https://community.sap.com/t5/supply-chain-management-q-a/anchor-time-period-in-ibp/qaq-p/12098710</link>
      <description>&lt;P&gt;Within IBP is it possible to 'anchor' a reference time period in IBP?&lt;/P&gt;
  &lt;P&gt;Example - &lt;/P&gt;
  &lt;P&gt;I want to setup a Calculated KF that will show me the values of the source KF, but only if it is the third month starting in Jan&lt;/P&gt;
  &lt;P&gt;&lt;IMG class="migrated-image" src="https://community.sap.com/legacyfs/online/storage/attachments/storage/7/attachments/1729518-example-anchor.jpg" /&gt;&lt;/P&gt;
  &lt;P&gt;Thanks in advance.&lt;/P&gt;
  &lt;P&gt;dan&lt;/P&gt;</description>
      <pubDate>Thu, 12 Sep 2019 18:39:45 GMT</pubDate>
      <guid>https://community.sap.com/t5/supply-chain-management-q-a/anchor-time-period-in-ibp/qaq-p/12098710</guid>
      <dc:creator>drbanning</dc:creator>
      <dc:date>2019-09-12T18:39:45Z</dc:date>
    </item>
    <item>
      <title>Re: 'Anchor' time period in IBP</title>
      <link>https://community.sap.com/t5/supply-chain-management-q-a/anchor-time-period-in-ibp/qaa-p/12098711#M171894</link>
      <description>&lt;P&gt;Hi Dan,&lt;/P&gt;&lt;P&gt;Here is what you can do. Create another Key Figure : helper and load that with a value 1, in the buckets you need the value output in another key figure. in your case, first month of every quarter. This could be a CPI-DS job  scheduled monthly or you can do that using a manually maintained file using data integration and keep updating the buckets each month and updating the key figure.&lt;/P&gt;&lt;P&gt;Once you've loaded the helper key figure with 1 for required buckets,  create another calculated key figure and put a calculation to check if the helper key figure is 1 then this calculated key figure gets value from source key figure, else default it to null.&lt;/P&gt;&lt;P&gt;Thanks,&lt;/P&gt;&lt;P&gt;Nikunj&lt;/P&gt;</description>
      <pubDate>Thu, 12 Sep 2019 18:59:09 GMT</pubDate>
      <guid>https://community.sap.com/t5/supply-chain-management-q-a/anchor-time-period-in-ibp/qaa-p/12098711#M171894</guid>
      <dc:creator>Former Member</dc:creator>
      <dc:date>2019-09-12T18:59:09Z</dc:date>
    </item>
  </channel>
</rss>
