    <title>Question Re: Actual dates in sap ppm in Product Lifecycle Management Q&amp;A</title>
    <link>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517763#M75993</link>
    <description>&lt;P&gt;Hi Paco &lt;/P&gt;&lt;P&gt;Thanks for the help. Could you please provide table details with dates. &lt;/P&gt;</description>
    <pubDate>Tue, 08 Mar 2022 05:50:54 GMT</pubDate>
    <dc:creator>yaswanthgopi</dc:creator>
    <dc:date>2022-03-08T05:50:54Z</dc:date>
    <item>
      <title>Actual dates in sap ppm</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaq-p/12517756</link>
      <description>&lt;P&gt;Hi Experts, &lt;/P&gt;
  &lt;P&gt;how do i get Actual dates in sap ppm. i.e (if a phase is closed need to get phase closed date ) and at the project closure need project closure date. &lt;/P&gt;
  &lt;P&gt;Regards&lt;/P&gt;
  &lt;P&gt;Gopi.&lt;/P&gt;</description>
      <pubDate>Mon, 07 Mar 2022 12:29:16 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaq-p/12517756</guid>
      <dc:creator>yaswanthgopi</dc:creator>
      <dc:date>2022-03-07T12:29:16Z</dc:date>
    </item>
    <item>
      <title>Re: Actual dates in sap ppm</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517757#M75987</link>
      <description>&lt;P&gt;Actual dates are written when you Confirm a Task.  There is an app for Confirming Tasks.  To get accurate scheduling you need to confirm a task when it is started and in process.  Confirm the Start Date and enter a POC or remaining work.&lt;/P&gt;</description>
      <pubDate>Mon, 07 Mar 2022 16:12:28 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517757#M75987</guid>
      <dc:creator>Ken_Melching</dc:creator>
      <dc:date>2022-03-07T16:12:28Z</dc:date>
    </item>
    <item>
      <title>Re: Actual dates in sap ppm</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517758#M75988</link>
      <description>&lt;P&gt;Hi Ken&lt;/P&gt;&lt;P&gt;How do I get Actual dates when the project and phase is completed &lt;/P&gt;</description>
      <pubDate>Mon, 07 Mar 2022 18:48:16 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517758#M75988</guid>
      <dc:creator>yaswanthgopi</dc:creator>
      <dc:date>2022-03-07T18:48:16Z</dc:date>
    </item>
    <item>
      <title>Re: Actual dates in sap ppm</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517759#M75989</link>
      <description>&lt;P&gt;Please give me more details on your question.&lt;/P&gt;&lt;P&gt;Do you know the actual dates and want to get them into the system?  &lt;/P&gt;&lt;P&gt;Or are you looking for them in the system?  If so, what processes are being followed? Are they confirming tasks?&lt;/P&gt;</description>
      <pubDate>Mon, 07 Mar 2022 18:56:08 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517759#M75989</guid>
      <dc:creator>Ken_Melching</dc:creator>
      <dc:date>2022-03-07T18:56:08Z</dc:date>
    </item>
    <item>
      <title>Re: Actual dates in sap ppm</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517760#M75990</link>
      <description>&lt;P&gt;Question is regarding how the actual dates gets updated for project and phase not for the task. I.e when I complete a specific phase will my phase actual dates get updated on the date of completion ?&lt;/P&gt;</description>
      <pubDate>Mon, 07 Mar 2022 19:01:53 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517760#M75990</guid>
      <dc:creator>yaswanthgopi</dc:creator>
      <dc:date>2022-03-07T19:01:53Z</dc:date>
    </item>
    <item>
      <title>Re: Actual dates in sap ppm</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517761#M75991</link>
      <description>&lt;P&gt;Actual dates are only entered on the tasks via confirmation.  These actual dates can be used to calculate the scheduled which will roll up to the Phases.&lt;/P&gt;</description>
      <pubDate>Mon, 07 Mar 2022 19:40:30 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517761#M75991</guid>
      <dc:creator>Ken_Melching</dc:creator>
      <dc:date>2022-03-07T19:40:30Z</dc:date>
    </item>
    <item>
      <title>Re: Actual dates in sap ppm</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517762#M75992</link>
      <description>&lt;P&gt;Hello.&lt;/P&gt;&lt;P&gt;The /S4PPM/TASK table may help you. &lt;/P&gt;&lt;P&gt;With a GUID or EXTERNAL_ID to identify the object, you can filter by object type (OBJECT_TYPE), e.g. PPO=Phase, DPO=Project,...).&lt;/P&gt;&lt;P&gt;You can also filter by status for each GUID/EXTERNAL_ID, e.g. if the object is completed (Completed=40).&lt;/P&gt;&lt;P&gt;With this information you can reach the ACTUALSTART and ACTUALFINISH of each object, corresponding to the dates.&lt;/P&gt;&lt;P&gt;&lt;IMG class="migrated-image" src="https://community.sap.com/legacyfs/online/storage/attachments/storage/7/attachments/2027804-image.png" /&gt;&lt;/P&gt;&lt;P&gt;I hope it helps you.&lt;/P&gt;</description>
      <pubDate>Mon, 07 Mar 2022 22:43:10 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517762#M75992</guid>
      <dc:creator>pacoginer</dc:creator>
      <dc:date>2022-03-07T22:43:10Z</dc:date>
    </item>
    <item>
      <title>Re: Actual dates in sap ppm</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517763#M75993</link>
      <description>&lt;P&gt;Hi Paco &lt;/P&gt;&lt;P&gt;Thanks for the help. Could you please provide table details with dates. &lt;/P&gt;</description>
      <pubDate>Tue, 08 Mar 2022 05:50:54 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517763#M75993</guid>
      <dc:creator>yaswanthgopi</dc:creator>
      <dc:date>2022-03-08T05:50:54Z</dc:date>
    </item>
    <item>
      <title>Re: Actual dates in sap ppm</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517764#M75994</link>
      <description>&lt;P&gt;Hi Paco &lt;/P&gt;&lt;P&gt;Actual Dates are updating  only for tasks. could you Suggest how does the Actual dates Roll up to the phase and project. &lt;/P&gt;&lt;P&gt;Thanks&lt;/P&gt;&lt;P&gt;Gopi.&lt;/P&gt;</description>
      <pubDate>Tue, 08 Mar 2022 07:58:16 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/actual-dates-in-sap-ppm/qaa-p/12517764#M75994</guid>
      <dc:creator>yaswanthgopi</dc:creator>
      <dc:date>2022-03-08T07:58:16Z</dc:date>
    </item>
  </channel>
</rss>
