<?xml version="1.0" encoding="UTF-8"?>
<rss xmlns:content="http://purl.org/rss/1.0/modules/content/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:rdf="http://www.w3.org/1999/02/22-rdf-syntax-ns#" xmlns:taxo="http://purl.org/rss/1.0/modules/taxonomy/" version="2.0">
  <channel>
    <title>Question Re: Transfer planned time from cProjects to CATS worklist in Product Lifecycle Management Q&amp;A</title>
    <link>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836950#M54226</link>
    <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Hi Clara!,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Thanks for your quickly reply,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Yes, Sap help says that this functionaliy is included in ECC 6.0 EhP3 and our system is ECC 6.0 EhP6, but I don't get it. &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;&lt;SPAN style="font-size: 10pt;"&gt;It's posible that the problem will be in the unit of measurement but I'm not sure. I'm going to try differents combinations between days and hours. &lt;/SPAN&gt;&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;&lt;SPAN style="font-size: 10pt;"&gt;Do you have any idea to resolve it?&lt;/SPAN&gt;&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;&lt;SPAN style="font-size: 10pt;"&gt;Regards&lt;BR /&gt;&lt;/SPAN&gt;&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
    <pubDate>Tue, 19 Nov 2013 07:24:57 GMT</pubDate>
    <dc:creator>Former Member</dc:creator>
    <dc:date>2013-11-19T07:24:57Z</dc:date>
    <item>
      <title>Transfer planned time from cProjects to CATS worklist</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaq-p/9836948</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Hi all,&lt;/P&gt;&lt;P&gt;At the moment we are evaluating cProjects 5.0 and we use CATS to confirm on the task level. This works fine, we can confirm them but we cannot display the planned time in the worklist.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;This would be useful for the confirm task because we will only copy the row and confirm it. &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;&lt;IMG class="migrated-image" src="https://community.sap.com/legacyfs/online/storage/attachments/storage/7/jiveimages/326084" width="450" /&gt;&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt; If we make the workforce planning of a resource in a activity of a project&amp;nbsp; PS we will see the planned time in the worklist of CATS. &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;&lt;IMG class="migrated-image" src="https://community.sap.com/legacyfs/online/storage/attachments/storage/7/jiveimages/326085" width="450" /&gt;&lt;/P&gt;&lt;P&gt;Is possible make the transfer of planned time of the task to CAT2?&amp;nbsp; Are we missing anything?&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Regards,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Kike&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Mon, 18 Nov 2013 19:31:35 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaq-p/9836948</guid>
      <dc:creator>Former Member</dc:creator>
      <dc:date>2013-11-18T19:31:35Z</dc:date>
    </item>
    <item>
      <title>Re: Transfer planned time from cProjects to CATS worklist</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836949#M54225</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;HI Enrique,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;If I am not wrong&amp;nbsp; this functionality is included in&amp;nbsp; ECC 6.0 EhP3. Could you check your EhP?&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Regards&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Mon, 18 Nov 2013 21:41:43 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836949#M54225</guid>
      <dc:creator>former_member209919</dc:creator>
      <dc:date>2013-11-18T21:41:43Z</dc:date>
    </item>
    <item>
      <title>Re: Transfer planned time from cProjects to CATS worklist</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836950#M54226</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Hi Clara!,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Thanks for your quickly reply,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Yes, Sap help says that this functionaliy is included in ECC 6.0 EhP3 and our system is ECC 6.0 EhP6, but I don't get it. &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;&lt;SPAN style="font-size: 10pt;"&gt;It's posible that the problem will be in the unit of measurement but I'm not sure. I'm going to try differents combinations between days and hours. &lt;/SPAN&gt;&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;&lt;SPAN style="font-size: 10pt;"&gt;Do you have any idea to resolve it?&lt;/SPAN&gt;&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;&lt;SPAN style="font-size: 10pt;"&gt;Regards&lt;BR /&gt;&lt;/SPAN&gt;&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Tue, 19 Nov 2013 07:24:57 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836950#M54226</guid>
      <dc:creator>Former Member</dc:creator>
      <dc:date>2013-11-19T07:24:57Z</dc:date>
    </item>
    <item>
      <title>Re: Transfer planned time from cProjects to CATS worklist</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836951#M54227</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Hi Enrique,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Not sure, it is possible. Check if you have configured in ECC --&amp;gt; SPRO --&amp;gt; Portfolio and Project management --&amp;gt; Portfolio management --&amp;gt; Convert Working Time units&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Regards&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Tue, 19 Nov 2013 18:36:55 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836951#M54227</guid>
      <dc:creator>former_member209919</dc:creator>
      <dc:date>2013-11-19T18:36:55Z</dc:date>
    </item>
    <item>
      <title>Re: Transfer planned time from cProjects to CATS worklist</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836952#M54228</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Hi Clara,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;No. Convert working time units is clear. &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Do you see the planned time of the rol or task from cProjects in the worklist of CAT2? Not sure if this is possible.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;We can cofirm without any problem for this reason we are confused if this is possible or not. At moment I have been searched in the project types of cProjects and data entry profile of CATS. We have created our own.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Regards.&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Tue, 19 Nov 2013 19:27:53 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836952#M54228</guid>
      <dc:creator>Former Member</dc:creator>
      <dc:date>2013-11-19T19:27:53Z</dc:date>
    </item>
    <item>
      <title>Re: Transfer planned time from cProjects to CATS worklist</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836953#M54229</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Hi Enrique,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Check whether have you enabled capacity distribution in the project role type.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Further details can also be brought in CAT2 time confirmation like remaining work time or percentage complete by activating the business function 'CA_CATS_CPR_CORE' &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;You can use this business function to implement the time sheet as a single point of entry for entering project time confirmations. It enables your employees to simultaneously save confirmation details for &lt;SPAN class="SAPXDPProductName "&gt;collaboration projects&lt;/SPAN&gt; (&lt;SPAN class="SAPXDPProductName "&gt;cProjects&lt;/SPAN&gt;), such as &lt;STRONG&gt;remaining work time or percentage complete&lt;/STRONG&gt;, when recording working times with the &lt;SPAN class="SAPXDPProductName "&gt;CATS classic&lt;/SPAN&gt; application.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;For details, you can refer the below link.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;&lt;A href="http://help.sap.com/erp2005_ehp_03/helpdata/EN/5A/45F204CBD243CD91062C81A4169146/frameset.htm" title="http://help.sap.com/erp2005_ehp_03/helpdata/EN/5A/45F204CBD243CD91062C81A4169146/frameset.htm"&gt;http://help.sap.com/erp2005_ehp_03/helpdata/EN/5A/45F204CBD243CD91062C81A4169146/frameset.htm&lt;/A&gt;&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Regards,&lt;/P&gt;&lt;P&gt;Ravi&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Wed, 20 Nov 2013 06:09:02 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836953#M54229</guid>
      <dc:creator>ravi_ekambaram</dc:creator>
      <dc:date>2013-11-20T06:09:02Z</dc:date>
    </item>
    <item>
      <title>Re: Transfer planned time from cProjects to CATS worklist</title>
      <link>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836954#M54230</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Hi to both,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;First of all&amp;nbsp; I should like to thank both&amp;nbsp; for your quickly reply. &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Ravi the capacity distribution in the project role type is active and our system we have implemented the BF CA_CATS_CPR_CORE.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;On the one hand I have checked the configuration of Project Role Types (everything seems correct) and the report Capacity evaluation CM51 in which the Remaining capacity reqmts per period is 0. It is normal since this is for activities and in cProject I have got WBS.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;On the other hand we have seen that when copy row from worklist (the task or rol is the same) to data entry area we can see the project information (F9) and in this windows we can see planned work, but not before. &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;I’m going to search some note about this.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;If you have got some idea please write.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Thanks a lot.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Regards.&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Wed, 20 Nov 2013 10:56:19 GMT</pubDate>
      <guid>https://community.sap.com/t5/product-lifecycle-management-q-a/transfer-planned-time-from-cprojects-to-cats-worklist/qaa-p/9836954#M54230</guid>
      <dc:creator>Former Member</dc:creator>
      <dc:date>2013-11-20T10:56:19Z</dc:date>
    </item>
  </channel>
</rss>

