<?xml version="1.0" encoding="UTF-8"?>
<rss xmlns:content="http://purl.org/rss/1.0/modules/content/" xmlns:dc="http://purl.org/dc/elements/1.1/" xmlns:rdf="http://www.w3.org/1999/02/22-rdf-syntax-ns#" xmlns:taxo="http://purl.org/rss/1.0/modules/taxonomy/" version="2.0">
  <channel>
    <title>Question Re: Raw materials planning in HANA, FG planning/scheduling in PPDS in Enterprise Resource Planning Q&amp;A</title>
    <link>https://community.sap.com/t5/enterprise-resource-planning-q-a/raw-materials-planning-in-hana-fg-planning-scheduling-in-ppds/qaa-p/13602990#M4179528</link>
    <description>Any help is appreciated</description>
    <pubDate>Mon, 12 Feb 2024 21:02:43 GMT</pubDate>
    <dc:creator>swathi_rege</dc:creator>
    <dc:date>2024-02-12T21:02:43Z</dc:date>
    <item>
      <title>Raw materials planning in HANA, FG planning/scheduling in PPDS</title>
      <link>https://community.sap.com/t5/enterprise-resource-planning-q-a/raw-materials-planning-in-hana-fg-planning-scheduling-in-ppds/qaq-p/13601124</link>
      <description>&lt;P&gt;Hi PPDS experts,&lt;/P&gt;&lt;P&gt;If I Plan and schedule FG in PPDS, but plan raw materials in HANA..how do we change the dates of raw material purchase reqs based on the new scheduling dates of finished goods in PPDS..&lt;/P&gt;&lt;P&gt;If I use PPDS for both FG and raw materials, I can run top down heuristic to align the whole BOM chain based on my FG new scheduled date..but if I use HANA for raw materials, how do I get the visibility to change raw material procurement dates as the FG scheduling dates have been changed in ppds?&lt;/P&gt;&lt;P&gt;&lt;a href="https://community.sap.com/t5/user/viewprofilepage/user-id/188408"&gt;@tiago_furlanetto&lt;/a&gt;&amp;nbsp;&lt;a href="https://community.sap.com/t5/user/viewprofilepage/user-id/239223"&gt;@yasmin_alayyan&lt;/a&gt;&amp;nbsp;&lt;/P&gt;&lt;P&gt;&amp;nbsp;&lt;/P&gt;&lt;P&gt;&amp;nbsp;&lt;/P&gt;</description>
      <pubDate>Wed, 14 Feb 2024 14:26:24 GMT</pubDate>
      <guid>https://community.sap.com/t5/enterprise-resource-planning-q-a/raw-materials-planning-in-hana-fg-planning-scheduling-in-ppds/qaq-p/13601124</guid>
      <dc:creator>swathi_rege</dc:creator>
      <dc:date>2024-02-14T14:26:24Z</dc:date>
    </item>
    <item>
      <title>Re: Raw materials planning in HANA, FG planning/scheduling in PPDS</title>
      <link>https://community.sap.com/t5/enterprise-resource-planning-q-a/raw-materials-planning-in-hana-fg-planning-scheduling-in-ppds/qaa-p/13602990#M4179528</link>
      <description>Any help is appreciated</description>
      <pubDate>Mon, 12 Feb 2024 21:02:43 GMT</pubDate>
      <guid>https://community.sap.com/t5/enterprise-resource-planning-q-a/raw-materials-planning-in-hana-fg-planning-scheduling-in-ppds/qaa-p/13602990#M4179528</guid>
      <dc:creator>swathi_rege</dc:creator>
      <dc:date>2024-02-12T21:02:43Z</dc:date>
    </item>
    <item>
      <title>Re: Raw materials planning in HANA, FG planning/schedulin...</title>
      <link>https://community.sap.com/t5/enterprise-resource-planning-q-a/raw-materials-planning-in-hana-fg-planning-scheduling-in-ppds/qaa-p/13625808#M4181300</link>
      <description>&lt;P&gt;Any insight?&lt;/P&gt;</description>
      <pubDate>Sat, 02 Mar 2024 04:43:06 GMT</pubDate>
      <guid>https://community.sap.com/t5/enterprise-resource-planning-q-a/raw-materials-planning-in-hana-fg-planning-scheduling-in-ppds/qaa-p/13625808#M4181300</guid>
      <dc:creator>swathi_rege</dc:creator>
      <dc:date>2024-03-02T04:43:06Z</dc:date>
    </item>
    <item>
      <title>Re: Raw materials planning in HANA, FG planning/schedulin...</title>
      <link>https://community.sap.com/t5/enterprise-resource-planning-q-a/raw-materials-planning-in-hana-fg-planning-scheduling-in-ppds/qaa-p/13634974#M4181975</link>
      <description>&lt;P&gt;Hello Swathi,&amp;nbsp;&lt;/P&gt;&lt;P&gt;&amp;nbsp;&lt;/P&gt;&lt;P&gt;This functionality is part of standard S/4 HANA Planning with PPDS. Have you gone through this help document?&lt;/P&gt;&lt;P&gt;&lt;A href="https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f899ce30af9044299d573ea30b533f1c/aa35c95360267514e10000000a174cb4.html?version=2022.000&amp;amp;q=" target="_blank"&gt;https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f899ce30af9044299d573ea30b533f1c/aa35c95360267514e10000000a174cb4.html?version=2022.000&amp;amp;q=&lt;/A&gt;&lt;/P&gt;&lt;P&gt;Regards&lt;/P&gt;&lt;P&gt;Gaurav&lt;/P&gt;</description>
      <pubDate>Tue, 12 Mar 2024 06:14:44 GMT</pubDate>
      <guid>https://community.sap.com/t5/enterprise-resource-planning-q-a/raw-materials-planning-in-hana-fg-planning-scheduling-in-ppds/qaa-p/13634974#M4181975</guid>
      <dc:creator>guglanigaurav198768</dc:creator>
      <dc:date>2024-03-12T06:14:44Z</dc:date>
    </item>
  </channel>
</rss>

