    <title>Question Re: Exceeded budget Error even there's really enough budget in Project System in Enterprise Resource Planning Q&amp;A</title>
    <link>https://community.sap.com/t5/enterprise-resource-planning-q-a/exceeded-budget-error-even-there-s-really-enough-budget-in-project-system/qaa-p/12355686#M4012804</link>
    <description>&lt;P&gt;Dear Sridhar,&lt;/P&gt;&lt;P&gt;I would say that the method you are suggesting should be the last option and not the first option.&lt;/P&gt;&lt;P&gt;I'd rather start with the Availability Control Analysis report that is listing line items and its relevance for the assigned value.  Most of time this is rather a misinterpretation by the business user or a kind of training gap.  For example, Remaining order plan (ROP) is a budget relevant figure that most of users would ignore. It can be some "forgotten" PR, it can be no budget carry-forward from last year and so on...&lt;/P&gt;&lt;P&gt;Regards,&lt;/P&gt;&lt;P&gt;Paulo&lt;/P&gt;</description>
    <pubDate>Fri, 12 Mar 2021 17:51:56 GMT</pubDate>
    <dc:creator>Paulo_Vitoriano</dc:creator>
    <dc:date>2021-03-12T17:51:56Z</dc:date>
    <item>
      <title>Exceeded budget Error even there's really enough budget in Project System</title>
      <link>https://community.sap.com/t5/enterprise-resource-planning-q-a/exceeded-budget-error-even-there-s-really-enough-budget-in-project-system/qaq-p/12355684</link>
      <description>&lt;P&gt;Dear Friends,&lt;/P&gt;
  &lt;P&gt;In the project systems, The user is getting Exceeded budget Error even there's really enough budget.&lt;/P&gt;
  &lt;P&gt;We suggest the user to execute Transaction code CJEN and CJBV to resolve the issue .&lt;/P&gt;
  &lt;P&gt;Is there any permanent solution for this ?&lt;/P&gt;
  &lt;P&gt;Please suggest in detail&lt;/P&gt;
  &lt;P&gt;Regards&lt;/P&gt;
  &lt;P&gt;Sridhar&lt;/P&gt;</description>
      <pubDate>Fri, 12 Mar 2021 16:59:16 GMT</pubDate>
      <guid>https://community.sap.com/t5/enterprise-resource-planning-q-a/exceeded-budget-error-even-there-s-really-enough-budget-in-project-system/qaq-p/12355684</guid>
      <dc:creator>sridhar_muthekepalli3</dc:creator>
      <dc:date>2021-03-12T16:59:16Z</dc:date>
    </item>
    <item>
      <title>Re: Exceeded budget Error even there's really enough budget in Project System</title>
      <link>https://community.sap.com/t5/enterprise-resource-planning-q-a/exceeded-budget-error-even-there-s-really-enough-budget-in-project-system/qaa-p/12355685#M4012803</link>
      <description>&lt;P&gt;Budget can be spread out over time and down the project hierarchy.  Check the allocated budget in the correct time slot and hierarchy.&lt;/P&gt;</description>
      <pubDate>Fri, 12 Mar 2021 17:22:26 GMT</pubDate>
      <guid>https://community.sap.com/t5/enterprise-resource-planning-q-a/exceeded-budget-error-even-there-s-really-enough-budget-in-project-system/qaa-p/12355685#M4012803</guid>
      <dc:creator>Ken_Melching</dc:creator>
      <dc:date>2021-03-12T17:22:26Z</dc:date>
    </item>
    <item>
      <title>Re: Exceeded budget Error even there's really enough budget in Project System</title>
      <link>https://community.sap.com/t5/enterprise-resource-planning-q-a/exceeded-budget-error-even-there-s-really-enough-budget-in-project-system/qaa-p/12355686#M4012804</link>
      <description>&lt;P&gt;Dear Sridhar,&lt;/P&gt;&lt;P&gt;I would say that the method you are suggesting should be the last option and not the first option.&lt;/P&gt;&lt;P&gt;I'd rather start with the Availability Control Analysis report that is listing line items and its relevance for the assigned value.  Most of time this is rather a misinterpretation by the business user or a kind of training gap.  For example, Remaining order plan (ROP) is a budget relevant figure that most of users would ignore. It can be some "forgotten" PR, it can be no budget carry-forward from last year and so on...&lt;/P&gt;&lt;P&gt;Regards,&lt;/P&gt;&lt;P&gt;Paulo&lt;/P&gt;</description>
      <pubDate>Fri, 12 Mar 2021 17:51:56 GMT</pubDate>
      <guid>https://community.sap.com/t5/enterprise-resource-planning-q-a/exceeded-budget-error-even-there-s-really-enough-budget-in-project-system/qaa-p/12355686#M4012804</guid>
      <dc:creator>Paulo_Vitoriano</dc:creator>
      <dc:date>2021-03-12T17:51:56Z</dc:date>
    </item>
    <item>
      <title>Re: Exceeded budget Error even there's really enough budget in Project System</title>
      <link>https://community.sap.com/t5/enterprise-resource-planning-q-a/exceeded-budget-error-even-there-s-really-enough-budget-in-project-system/qaa-p/12355687#M4012805</link>
      <description>&lt;P&gt;Hi Sridhar,&lt;/P&gt;&lt;P&gt;If system is throwing an error
that means Availability Control is active.&lt;/P&gt;&lt;P&gt;Before executing transaction CJBN
Check your budget profile (T code - OPS9).&lt;/P&gt;&lt;P&gt;Please check whether you have
ticked&lt;/P&gt;&lt;P&gt;1. "Total values" in
the Timeframe block&lt;BR /&gt;
2. "Annual values" in the Timeframe block&lt;BR /&gt;
3. All four fields in the "Availability Control" block&lt;/P&gt;&lt;P&gt;Please
check your tolerance limit of the budget profile. Based on this, budget
functionality will work in project&lt;/P&gt;&lt;P&gt;Check
your tolerance limit SPRO --&amp;gt; PS --&amp;gt; COSTS --&amp;gt; Budget --&amp;gt; Tolerance
limit.&lt;/P&gt;&lt;P&gt;Change
Transaction group (01 or ++) change the usage to 100%.&lt;/P&gt;&lt;P&gt;If all
this is OK you can execute transaction CJBN in order to repair availability
budget...&lt;/P&gt;&lt;P&gt;Just
try to deactivate availability control, refresh project data base and activate
the availability control.&lt;/P&gt;&lt;P&gt;1. Deactivate
availability control: (T code - CJBW).&lt;/P&gt;&lt;P&gt;2. Refresh
data base: (T code - CJEN).&lt;/P&gt;&lt;P&gt;3.
Activate availability control: (T code - CJBV).&lt;/P&gt;&lt;P&gt;Thank You,&lt;/P&gt;&lt;P&gt;Regards,&lt;/P&gt;&lt;P&gt;Bhoomika SS &lt;/P&gt;</description>
      <pubDate>Tue, 30 Mar 2021 06:10:13 GMT</pubDate>
      <guid>https://community.sap.com/t5/enterprise-resource-planning-q-a/exceeded-budget-error-even-there-s-really-enough-budget-in-project-system/qaa-p/12355687#M4012805</guid>
      <dc:creator>former_member733958</dc:creator>
      <dc:date>2021-03-30T06:10:13Z</dc:date>
    </item>