    <title>topic Re: PROBLEMS WITH BACKGROUND JOB SCHEDULING WITH MULTIPLE STEPS in Application Development and Automation Discussions</title>
    <link>https://community.sap.com/t5/application-development-and-automation-discussions/problems-with-background-job-scheduling-with-multiple-steps/m-p/5146584#M1192664</link>
    <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Hi Shiva,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;           Defining the background job using SM36 will be executed in sequential order.  Step 1, Step 2 &amp;amp; Step 3.  Output of Step 1 might be the input for the Step 2 and output of Step 2 might be input for Step 3.  So they will be executed in sequential order.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;           Let me know if more details are required.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Regards&lt;/P&gt;&lt;P&gt;Sravan&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
    <pubDate>Mon, 02 Feb 2009 20:53:54 GMT</pubDate>
    <dc:creator>Former Member</dc:creator>
    <dc:date>2009-02-02T20:53:54Z</dc:date>
    <item>
      <title>PROBLEMS WITH BACKGROUND JOB SCHEDULING WITH MULTIPLE STEPS</title>
      <link>https://community.sap.com/t5/application-development-and-automation-discussions/problems-with-background-job-scheduling-with-multiple-steps/m-p/5146582#M1192662</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;HI Guys&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Hope you are all doing well and good !!&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Can you please update me is there any way to give a Constrain while Defining Multiple Steps for a Particular Job in SAP &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;i.e For Example..Until Unless STEP 2 is finished STEP 3 should not be executed &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Please update me if you have any answers&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Thanks in advance&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Regards&lt;/P&gt;&lt;P&gt;Shivakumar Bandari&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Mon, 02 Feb 2009 17:36:46 GMT</pubDate>
      <guid>https://community.sap.com/t5/application-development-and-automation-discussions/problems-with-background-job-scheduling-with-multiple-steps/m-p/5146582#M1192662</guid>
      <dc:creator>Former Member</dc:creator>
      <dc:date>2009-02-02T17:36:46Z</dc:date>
    </item>
    <item>
      <title>Re: PROBLEMS WITH BACKGROUND JOB SCHEDULING WITH MULTIPLE STEPS</title>
      <link>https://community.sap.com/t5/application-development-and-automation-discussions/problems-with-background-job-scheduling-with-multiple-steps/m-p/5146583#M1192663</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Hi Shiva,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;When you define steps in a background Job, they get executed in the sequence mentioned.&lt;/P&gt;&lt;P&gt;Step2 will not get executed unless and untill step1 has been succesfully executed and so on. This is by default.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Also, you can use AFTER JOB as your start condition.....this is just a workaround....&lt;/P&gt;&lt;P&gt;Create different Background jobs and select START CONDITION as the PREVIOUS JOB NAME that you want it to depend upon.....&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Best Regards,&lt;/P&gt;&lt;P&gt;Ankit Kumar&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Mon, 02 Feb 2009 17:59:51 GMT</pubDate>
      <guid>https://community.sap.com/t5/application-development-and-automation-discussions/problems-with-background-job-scheduling-with-multiple-steps/m-p/5146583#M1192663</guid>
      <dc:creator>ankit_kishorilalkedia</dc:creator>
      <dc:date>2009-02-02T17:59:51Z</dc:date>
    </item>
    <item>
      <title>Re: PROBLEMS WITH BACKGROUND JOB SCHEDULING WITH MULTIPLE STEPS</title>
      <link>https://community.sap.com/t5/application-development-and-automation-discussions/problems-with-background-job-scheduling-with-multiple-steps/m-p/5146584#M1192664</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Hi Shiva,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;           Defining the background job using SM36 will be executed in sequential order.  Step 1, Step 2 &amp;amp; Step 3.  Output of Step 1 might be the input for the Step 2 and output of Step 2 might be input for Step 3.  So they will be executed in sequential order.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;           Let me know if more details are required.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Regards&lt;/P&gt;&lt;P&gt;Sravan&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Mon, 02 Feb 2009 20:53:54 GMT</pubDate>
      <guid>https://community.sap.com/t5/application-development-and-automation-discussions/problems-with-background-job-scheduling-with-multiple-steps/m-p/5146584#M1192664</guid>
      <dc:creator>Former Member</dc:creator>
      <dc:date>2009-02-02T20:53:54Z</dc:date>
    </item>
    <item>
      <title>Re: PROBLEMS WITH BACKGROUND JOB SCHEDULING WITH MULTIPLE STEPS</title>
      <link>https://community.sap.com/t5/application-development-and-automation-discussions/problems-with-background-job-scheduling-with-multiple-steps/m-p/5146585#M1192665</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Thanks fro the Reply Shravan and Ankit&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;I will eloborate my query&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;I have step1 which Creates a Session for Sales order using a ZPROGRAM and Step2 to process that session using RSBDCSUB and Step 3 to update the order created  in Ztable and also it updates the header and item text, created for the sales order&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;When I Schedule the Job with this three steps. It looks like JOB log shows that Step3 has started successfully but there is no spool generated and also the ZTABLE with the new Order created is not getting updated. It is as simple as step3 as not at all run&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;When I Run the STEP3 as the seperate Job a Spool gets created for it and also it updates ZTABLE,Header texts and Items texts successfully. &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;In this Process I have understood that this is because of my second step being  a processing of session and third started which could not find input from the second Step hence it failed to update anything.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;I know there is an option in REDWOOD Software to keep the constraint..which I cannot find in SAP.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Please update me if you have any updates or if you faced similar senario's or issues &lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Regards&lt;/P&gt;&lt;P&gt;Shivakumar&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Mon, 02 Feb 2009 22:20:30 GMT</pubDate>
      <guid>https://community.sap.com/t5/application-development-and-automation-discussions/problems-with-background-job-scheduling-with-multiple-steps/m-p/5146585#M1192665</guid>
      <dc:creator>Former Member</dc:creator>
      <dc:date>2009-02-02T22:20:30Z</dc:date>
    </item>
    <item>
      <title>Re: PROBLEMS WITH BACKGROUND JOB SCHEDULING WITH MULTIPLE STEPS</title>
      <link>https://community.sap.com/t5/application-development-and-automation-discussions/problems-with-background-job-scheduling-with-multiple-steps/m-p/5146586#M1192666</link>
      <description>&lt;HTML&gt;&lt;HEAD&gt;&lt;/HEAD&gt;&lt;BODY&gt;&lt;P&gt;Hi Shiva,&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;I have not faced any such scenario so not sure how will this workout, but you can try the following:&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;1) Create 1st Background Job with STEP 1 and STEP2&lt;/P&gt;&lt;P&gt;2) Create 2nd Background Job with STEP 3 alone in it, &lt;/P&gt;&lt;P&gt;    Make sure that you assign 1st background Job as the start condition for the 2nd Background Job.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Hope This Helps.&lt;/P&gt;&lt;P&gt;&lt;/P&gt;&lt;P&gt;Regards,&lt;/P&gt;&lt;P&gt;Ankit Kumar&lt;/P&gt;&lt;/BODY&gt;&lt;/HTML&gt;</description>
      <pubDate>Mon, 02 Feb 2009 23:01:04 GMT</pubDate>
      <guid>https://community.sap.com/t5/application-development-and-automation-discussions/problems-with-background-job-scheduling-with-multiple-steps/m-p/5146586#M1192666</guid>
      <dc:creator>ankit_kishorilalkedia</dc:creator>
      <dc:date>2009-02-02T23:01:04Z</dc:date>
    </item>
  </channel>
</rss>
